New Main Library in the Park

New Main Library Site Map Thumbnail

Schematic plans presented February 19, 2009:

New Main Library in the Park, Site Plan

New Main Library in the Park: Building Section 

New Main Library in the Park, First Floor

New Main Library in the Park, Second Floor

New Main Library in the Park, Third Floor 

Tentative Construction Time Line:

  • Design Phase: February 27 through August 21, 2008
  • Public Meeting to present various Design Concepts: August 14, 2008
  • Revised Building Program, incorporating Genealogy Collection and BR Room : October 2, 2008
  • Schematic Design Phase: October 3, 2008 through March 2, 2009
  • Schematic Design Presentation: February 19, 2009
  • Design Development Phase: March 3 through July 1, 2009
  • Prepare Construction Documents: August 1, 2009 through February 17, 2010
  • Public Bid Phase: February 18 through April 19, 2010
  • Construction begins: April 19, 2010 (approximately 18 months)
  • Building completion, furniture installation, move in: Spring 2012